This work plan is developed following the outcome of the September 18, 2001 meeting of Canadian Council of Forest Ministers (CCFM) where support was given for the further development of NFIS beyond the progress reported on at the meeting.

The NFIS work plan for 2002-2003 is predicated upon the understanding that CCFM NFIS Steering Committee Members will be wholly engaged, committed to making progress on this initiative and will provide appropriate contact names as requested from time to time by the NFIS Project Office. All identified contacts will have been apprised by their Steering Committee Member of the support of their jurisdiction for the initiative and be ready to work with the NFIS Project Office and its associates in implementing an operational NFIS.

There are two dates that are recognized as critical to all CCFM members, those being associated with the CCFM Deputy Minister and Minister 2002 meetings in Nova Scotia during June and September, respectively. While these dates are critical for reporting purposes and the Project Office will conduct its work with the dates in mind, there are some activities that will not totally align with the meeting dates and therefore progress to date, rather than final, reports will be the products for the meetings.

A series of action items are set out for the coming fiscal year.

Action Items

1. ACTION: Identify and brief technical contacts on jurisdiction commitment to making progress on project.
RESPONSIBILITY Steering Committee Members
TIME FRAME Ongoing, as NFIS Project Office requests contacts.
2. ACTION: Define Application Services – 3 including one application using forest cover.
RESPONSIBILITY Steering Committee Members
TIME FRAME January 2002.
3. ACTION: Service Registries and Services Implementation development following definitions.
RESPONSIBILITY NFIS Project Office
TIME FRAME Proof of Concept March 2002, Implementation March 2003
4. ACTION: Prepare list of additional key information providers to be contacted, set priorities for contact and establish working contact. List may be affected by Application Services defined.
RESPONSIBILITY NFIS Project Office with input from Steering Committee.
TIME FRAME Input received by end of November 2001. Complete list by December 2001.
5. ACTION: Confirm key information.
RESPONSIBILITY NFIS Project Office, key information providers.
TIME FRAME starts January 2002.Linked to Application Services definition.
6. ACTION: Prepare Communications material.
RESPONSIBILITY NFIS Project Office
TIME FRAME Material ready for use by February 2002.
7. ACTION: Input to National Data Model Frameworks.
RESPONSIBILITY Key Information Providers, Steering Committee, NFIS Project Office.
TIME FRAME Ongoing and co-dependant with key information identification.
8. ACTION: Identify the order of remaining CCFM members for connectivity, taking into consideration the NFIS Project Office recommendation.
RESPONSIBILITY Steering Committee, NFIS Project Office.
TIME FRAME List prepared by December 2001.
9. ACTION: Promote NFIS technical developments and encourage key information providers to consider other business applications.
RESPONSIBILITY NFIS Project Office.
TIME FRAME Ongoing.
10. ACTION: Prepare list of additional key information providers to be contacted, set priorities for contact and establish working contact. List may be affected by Application Services defined.
RESPONSIBILITY NFIS Project Office with input from Steering Committee.
TIME FRAME Input received by end of November 2001. Complete list by December 2001.
11. ACTION: Ongoing associated with Action 16.
RESPONSIBILITY NFIS Project Office.
TIME FRAME Associated with connectivity priority.
12. ACTION: NFIS will develop Z39.50 based metadata services. NFIS supports the operation of a national NFIS Z39.50 server supporting distributed search through the GeoConnections CEONet Discovery Portal.
RESPONSIBILITY NFIS Project Office.
TIME FRAME Ongoing.
13. ACTION: Implement Z39.50 servers on entry level NFIS nodes as required; continue metadata tool developments and optimization.
RESPONSIBILITY NFIS Project Office.
TIME FRAME Ongoing.
14. ACTION: Implement Z39.50 servers on entry level NFIS nodes as required; continue metadata tool developments and optimization.
RESPONSIBILITY NFIS Project Office.
TIME FRAME Ongoing.
15. ACTION: Enhance tools to support reading native formats (initially ESRI and Intergraph/Bently).
RESPONSIBILITY NFIS Project Office.
TIME FRAME Ongoing as provincial/territorial NFIS nodes are implemented.
16. ACTION: Enhance capability and functionality of CCFM GeoExplore Web viewer; support enhancements to and deploy UMN Map Servers as required.
RESPONSIBILITY NFIS Project Office.
TIME FRAME Ongoing.
17. ACTION: Deployment of DACS framework at NFIS Project Office and on UMN Servers using file-based authentication following DACS delivery.
RESPONSIBILITY NFIS Project Office.
TIME FRAME DACS Contract deliverables expected February 2002. Deployment at pilot sites, using jurisdictional authentication mechanisms to be determined.
18. ACTION: Deploy and establish connectivity to distributed warehouses as required/scheduled.
RESPONSIBILITY NFIS Project Office.
TIME FRAME Associated with connectivity priority.
19. ACTION: Conduct proposed sessions with jurisdictions.
RESPONSIBILITY NFIS Project Office.
TIME FRAME Associated with connectivity priority.

NFIS 2002/2003 Activities

Deploy 5 (five) Provincial/Territorial OGC Compliant NFIS Web-servers (Actions 10, 16 and 17 of work plan)

  • Undertake Regional NFIS Joint Application Development sessions preparatory to deploying NFIS servers
  • Deploy Provincial/Territorial OGC Compliant NFIS Web-servers
Includes:
  • Server hardware and software
  • Load data
  • Integration of server into jurisdictional network

Deploy NFIS Distributed Access Control System (DACS) authentication against Provincial/Territorial servers (contract) (Action 15 of work plan)

Estimated Number of Installation sites = 8

Develop and Implement Service Registries (Action 3 of work plan)

Implementation operational NFDP Web forms data capture (Action 2 of work plan)

In-house NFIS Development Activities (Actions 3, 10, 11, 12, 13, 14 of work plan)

The following in-house development activities will be undertaken by NFIS Project Office CFS permanent and term appointment staff:

  • Implementation of service Discovery and Invocation through CCFM GeoExplore
  • Development of forest information services
    • Forest type distribution within ecozones
    • Forest type distribution by age class
    • Representation within protected areas
  • Registration of forest information services
  • Initial development of service authoring tool suite
  • MetaData tools development and enhancement
    • Automated extract form OGC Get Capabilities
    • Metadata lookup capability within NFIS Web Map clients
  • Distributed Access Control System enhancements
    • Pilot upgrading of NFIS Project Office server nodes to secured socket layer (SSL) web server, BC and Newfoundland to follow
    • Undertaking initial scooping of authentication against provincial/territorial server domains (BC and Newfoundland)
    • Initial investigations of the Deployment of Distributed Access Control System at Jurisdiction Pilot Sites – this initiative is designed to validate the Distributed Access Control System within diverse Web environments including Microsoft IIS, Apache and others.
  • Operation of NFIS Project Office Server and Services
    • National NFIS service registry
    • National Data Warehouse
    • National data content storage (CCFM NFDP,NFI/CANFI, Carbon, and NRCan National Topographic Database, Forest Health, etc.)
    • OGC Web Map and Web Feature services
    • National NFIS Metadata repository
  • Data presentation services
    • Graphical representation of results (user defined 3D, pie charts , etc.)
    • Metadata and data services for single or multiple features
    • Subject classification of information holdings
  • Web Services network monitoring
    • Development of Web Services monitoring tools
    • Application of Web Services tool
  • Development of named user session capabilities
    • User login and User groups
    • Saved content, state and profile
  • Simple feature geometry insert and annotation
  • Establish NFIS mirror site for serving Canada’s 1:50,000 and 1:250,000 NTS maps
spacer spacer
Français

This page was last updated on: 27-Apr-2006